1. Retrospective on Sprint 13

  • Waffle stories completed during the sprint:
    • Require a status to be selected when job seeker registers in PETS (#183)
    • Change testing framework for JavaScript(#222, #221)
    • Run cruncher on a Resume when it is uploaded
    • Basic matching system for Resumes based on title and description of jobs (#240, #239)
    • Corrected issue found on confirmation email(#238)
    • Manage Skills (#235)
  • Waffle stories worked on during the sprint:
    • Implement Job Seeker Home Page (#202)
    • Implement Job Developer Home Page(#226#229, #227)
    • Continue development for jobs (Associate a job with a company) (#192)
    • Notification system design (#186)
    • User Authorizations Matrix (#205)
2. Questions for the client
  • Regarding Employers
    • Whenever an employer (company) asks to be deleted from the system, what should we do? Effectively remove it, or flag it as removed and remove all external visible access to the company?
      • If we remove the company some questions arise, like what do we do with the Job they posted? what if the companies hired Job Seekers? (We believe this is not a good option because we will loose traceability of the action of the Job Seekers)
      • If we disable the company, we will block access to all jobs of the company, access of their logins(company employees), but we would keep all the relationships and actions between Job Seekers and Company
      • Another option is to remove the company and replace the company with a "dummy" company keeping all the relationships that exist between Job Seekers and the Company ( Ex: where you would have a relationship like "Job Seeker A applied to the job 'Job title' on the Company A" would be replaced by "Job Seeker A applied to the job with 'Job title' on a 'Dummy Removed company'")
  • Currently in the website we are studying 2 colours for the base, they can be seen in the header and in the footer of the page. What colour do you believe it looks best?(http://pets-dev.herokuapp.com)
3. Questions from the client
4. Priorities for next sprint ( sprint 14, starting Monday, 03/28/16 )

  • Delivery all stories listed above in "stories worked on during the sprint"
  • Job Developer Home page creation
  • Job Management system
  • Continue research and prototyping on Notification system

5. Schedule next client meeting for 04/08/2016 at 5.30pm EST