List of Projects MetPlus Client meetings Meeting 20 - 06/17/2016

Meeting 20 - 06/17/2016

Updated over 3 years ago by Patrick Bolger
Retrospective on Sprint 19

1. Waffle stories completed during the sprint:
  • Job Developer and Case Manager can self assign a Job Seeker(#341)
  • Job Developer Notified when a Job Seeker is assigned (#338)
  • Case Manager Notified when a Job Seeker is assigned (#344)
  • Allow company to have multiple addresses (these are used for specifying job location) (#345)
  • Allow Job Developers to create Jobs (#339)

2. Other Waffle stories worked on during the sprint:
  • Agency person home page
    • List all job seekers without a Case Manager (#234)
  • Code reuse and UI improvements on Agency Person Landing page (#314)
3. Questions for the client
4. Questions from the client

5. Priorities for next sprint ( sprint 20, starting Monday, 06/20/16 )

  • Delivery of most or all stories listed above in "stories worked on during the sprint"
  • Agency Person Home page enhancements (Code reuse and UI improvements)
  • Job Management system continued development, e.g.
    • Job life-cycle states (active, revoked, filled)
    • Allow company person and agency personnel (JD) to set status
  • Continue working on "job matching" features, for example:
    • Job seeker résumé match to jobs (show all matching jobs)
    • Job Developer matching job to job seekers' résumés (show all matching job seekers)
  • Allow company people to edit company information (e.g., add addresses/job locations)
  • Allow agency people to edit company information
  • Other stories from the project backlog

    5. Schedule next client meeting for 07/01/2016 at 5.30 pm EST

    6. Action points from this meeting: