Retrospective on Sprint 25 and 26

1. Waffle stories completed during the sprint:
  • Code enhancement:
    • Internal change in job status field (#402)
    • Code cleanup(#406)
    • Solve issues on testing (#408)
    • Refactoring Job Seeker model (#284)
  • Job Developer applies to a job on behalf of Job Seeker (#40)
  • JS ability to apply to job and information is sent to the Company(#386)
  • Categorization algorithm improvement for the Cruncher(#336, #419)
  • Handling task completion for agency admin (#342)
    • For example, the agency admin will have visibility to these tasks:
      • Unassigned agency tasks
      • Assigned (open) agency tasks (assigned to myself or others)
      • My open tasks
      • Closed agency tasks (including my own)
  • Add Job Status field when showing the jobs (#398)
  • Do not allow Job Seeker to apply to same job twice (#399)
  • Finalize the permission matrix (#407)
  • Selected "mailgun" service to send notification emails (#409)
  • Generalization of valid phone number (#413)
  • Company ability to change job email (#416)
  • Job Developer apply for a Job Seeker to a job (#418)
  • Allow Job Seeker control over Job Developer application to jobs (#410)
2. Other Waffle stories/items worked on during the sprint:
  • Ensure dates are in correct timezone(#292)
  • Add authorization for Company People(#434)
  • Allow Company person to open and close tasks (#424)
  • Notify Case Manager that Job Seeker was hired (#423)
  • Company Admin assign tasks to Company Admin and Contact(#426)
  • Add not_accepted as a state for a job application(#374)
  • Configure mailgun (#414)
  • Allow Case Manager to update Job Seeker information (#422)
  • Add authorization for Agency People (#433)
  • Update the resume after application submited (#427)
3. Questions for the client
  • Discuss possibility of change meeting time every other week to mornings to meet with all the team
    • 10 am is one possibility, or we can try to do it also saturday earlier
  • Developments on the DNS with iPages
4. Questions from the client

5. Priorities for next sprint ( sprint 26, starting Monday, 09/26/16 )

  • Job Management system continued development, e.g.
    • Implement feature to set job application to 'not_accepted'
  • Task Management
    • Provide visibility to tasks by task status
    • Enhance task assignment and view for company people
  • Confirm Job Seeker privacy controls and start development of features to implement those
  • Continue working on "job matching" features, for example:
    • Job seeker résumé match to jobs (show all matching jobs)
    • Job Developer matching job to job seekers' résumés (show all matching job seekers)
  • Begin implementation of authorization confirmation for system objects and features
    • For example, some features can only be accessed by an agency admin
  • Review "MVP List" in preparation for discussion at next client meeting

5. Schedule next client meeting for 10/07/2016 at 10 am EST

6. Action points from this meeting:
Revisions

comments powered by Disqus