List of Projects MetPlus Client meetings Meeting 32 - 12/19/2016

Meeting 32 - 12/19/2016

Updated almost 3 years ago by Joao Pereira
1. Retrospective on Sprint 31

1.1 Waffle stories completed during the sprint:
  • Added comment explaining how to define FIREFOX_BINARY_PATH # by (patmbolger)
  • Allow company person to contact JD for interest in JS #412 by (patmbolger)
  • Change selenium tests to use poltergeist #499 by (patmbolger)
       ===== Cruncher ====

1.2. Other Waffle stories/items worked on during the sprint:
2. Updates from AV
  • On verge of deliverying last MVP story
  • Talk about budget to production environment
    • 1 Application running/rails
    • 1 Postgres Database
    • 1 Application running/cruncher
    • 1 Mongo Database
    • Pusher account
    • Mailgun account
  • Drie option for Application(Rails) hosting
  • New page design
3. Questions for the client

4. Questions from the client

5. Priorities for next sprint ( sprint 33, starting Monday, 12/19/16 )
  • Complete all stories for MVP
  • Work on and refine production environment

6. Schedule next client meeting for Monday01/09/2017 at 12.30 pm EST

7. Action points from this meeting